date:2018-11-06 source:project management department author:wang yue

the full-power demonstration test run of sanmen unit2 was completed at 21:17 on 5th, november, 2018. the reactor has now been "put into commercial operation conditions". 

in september 2007, the construction of four ap1000 units in china was permitted by the authorisation: two at sanmen in zhejiang province and two more at haiyang in shandong province. construction of sanmen 1 began in april 2009, while first concrete for sanmen 2 was poured in december 2009.

ve0allurpx2asctfaaemmal1eoe571_meitu_2.jpg

the loading of fuel assemblies into its core began on 5 july. the unit achieved first criticality on 17 august. sanmen 2 was connected to the grid on 24 august, and reached 100% power for the first time on 30 september.

the successful construction of the sanmen nuclear power project is an important achievement in the development of china's third-generation of nuclear power plants, and will vigorously promote the industrialisation of china's independent passive nuclear power technology.