date:2019-01-10 source:president's office and international affairs author:bao li

on january 10, 2019, unit 2 of the haiyang nuclear power plant in china's shandong province has completed 168 hours of full-power continuous operation and is now deemed to be in commercial operation. it becomes the fourth ap1000 unit in china to reach the milestone.

20190109  海阳一期工程核岛照片_meitu_4.jpg

construction of sanmen 1, in zhejiang province, began in april 2009, while first concrete for sanmen 2 was poured in december 2009. construction of haiyang 1 and 2 began in september 2009 and june 2010, respectively.

sanmen 1 was the world's first ap1000 to start up, achieving first criticality - a sustained chain reaction - on 22 june last year and grid connection on 2 july. it reached full power operation for the first time on 14 august and entered commercial operation on 21 september.

unit 1 of the haiyang plant attained first criticality on 8 august and was grid connected on 17 august. that unit began commercial operation on 22 october.

sanmen unit 2 attained first criticality on 17 august and was connected to the grid on 24 august. the reactor entered commercial operation on 5 november.

haiyang 2 achieved first criticality on 29 september and was connected to the grid on 13 october.

together, haiyang units 1 and 2 will provide some 20 twh of electricity to the grid annually, sufficient to meet one-third of household demand in shandong province.

with the start of commercial operation of haiyang 2, mainland china now has 46 power reactors in operation with a combined installed capacity of more than 45 gwe.